🔥NEW I need to create a Gantt chart for a project, but I don't know the start date of the project. I need to display in the chart 0-36 months as time line and not a specific date. I didn't find a free software to do this. Do you have any idea? Thanks, Stefania. (...) Read more? Sign up for free

Please register now to read all responses and to join this discussion yourself. It's easy and 100% free.

Sign up for free     Log in


  Anonymous
 

How to Create a Gantt Chart Without a Start Date?

You can remove the milestone date by editing the bar style and removing the date. Typically you right click in the Gantt chart and choose, "Bar Styles" or similar.
Alternatively, you could change the display of the date format of the milestones through formatting the layout. Typically again you right click the chart and then choose "Layout".

 
More on Gantt Chart
Summary
Forum
Task and Bonus Wage System
Gantt or Pert in IT projects
Creating a Gantt Chart Without a Start Date
Special Interest Group Leader

Are you an expert in Gantt Chart? Sign up for free


Gantt Chart
Knowledge Center

 

Next Topic



About 12manage | Advertising | Link to us / Cite us | Privacy | Suggestions | Terms of Service
2020 12manage - The Executive Fast Track. V15.6 - Last updated: 27-10-2020. All names of their owners.