What is a Master Production Schedule (MPS)?




Capacity Planning
Knowledge Center

Translate

Forum
5
Andana
Analyst, Sweden

What is a Master Production Schedule (MPS)?

🔥NEW In short, an MP is a plan that details how many end items will be produced within specific periods of time.
A Master Production Schedule or MPS is the blueprint that a corporation has developed for manufacturing, inventory, staffing, etc. It sets the quantity of each end item to be realized in each week of a short-range planning horizon. A Master Production timetable is the master of all schedules. It is a plan for future production of end items (inventory solutions).

MPS INPUTS:
- Forecast Demand
- Production Costs
- Inventory Costs
- Customer Orders
- Inventory Levels
- Supply
- Lot Size
- Production Lead Time
- Capacity

MPS OUTPUT (production plan):
- Amounts to be Produced
- Staffing Levels
- Quantity Available to Promise
- Projected Available Balance
- (Inventory Solutions)

Developing a Master Production Schedule requires:
1. Calculating the projected on-hand inventory, and
2. Determining the timing and size of production quantities of specific products (Krajewski)
Sources:
Inventory Solutions Logistics Corp, " The Master Production Schedule", 2007
Krajewski, Ritzman, Malhorortra, "Operations Management', 9th Edition, Prentice Hall, (p. 547).
.

   

More on Capacity Planning:
Summary
Discussion Topics
👀What is a Master Production Schedule (MPS)?
Two Ways to Measure Capacity
Special Interest Group

Do you know a lot about Capacity Planning? Become our SIG Leader

Capacity Planning
Knowledge Center



About 12manage | Advertising | Link to us / Cite us | Privacy | Suggestions | Terms of Service
© 2023 12manage - The Executive Fast Track. V16.1 - Last updated: 29-3-2023. All names ™ of their owners.